ERCOT isolation, interconnection pace, water and community process vary by county. Mousterian has named a Houston-area floating/hybrid concept (Project Zeus) as a plan — not an energised campus.
REQUIRES VERIFICATIONPreliminary
Large and growing. Treat developer MW as announced until interconnection is real.
Cartographic night
Evidence
- Moderate confidenceProposed
The Mousterian–Samsung Heavy engineering contract describes purpose-built moored floating data-centre units each delivering 50 MW of critical IT capacity, with non-evaporative cooling and no potable water consumption claimed.
PR Newswire · Mousterian and Samsung Heavy sign engineering contract for first US floating data center · published 2026-08-03 · accessed 2026-09-18