Projects
Announced ≠ approved ≠ power secured ≠ built
The seed mixes data-centre projects, enabling works, storage, transmission and cables so the funnel cannot pretend they are the same object.
| Project | Stage | Announced MW | Power secured | Status |
|---|---|---|---|---|
| CopperString Eastern Link Transmission, not a data centre. In the project list because it is the principal committed energy fact for Townsville-scale industrial load in the 2030s. | electrical infrastructure | — | — | LIVEHigh confidence |
| Supernode North BESS (Solquartz) Three 260 MW / 8 h batteries. Storage for industrial/silicon, not a compute campus. Announced MW is BESS power, not IT load. | planning lodged | 780 | — | REQUIRES VERIFICATIONModerate confidence |
| NQ SPARK Simulation and HPC facility (~1,100 m²). Proposition B, not Proposition A. | operational | — | — | LIVEHigh confidence |
| Liddell Battery Do not file this as a 500 MW data centre. | operational | 500 | 500 | LIVEVerified |
| Beetaloo Digital — Weddell Site exclusivity and GW-scale statements. Announced ≠ approved ≠ power secured ≠ financed. | announced | 1000 | — | REQUIRES VERIFICATIONPreliminary |
| NEXTDC D1 Darwin Up to 7 MW IT. Not Weddell. | operational | 7 | 7 | LIVEHigh confidence |
| Vocus Darwin–Jakarta–Singapore Cable Cable, not a data centre. In the project list because it is the principal fibre fact for Darwin. | operational | — | — | LIVEVerified |
| NEXTDC PH1 Port Hedland 1.5 MW planned IT. Cyclone-rated edge. Not hyperscale. | operational | 1.5 | 1.5 | LIVEHigh confidence |
| Vocus Horizon 2,000 km Perth–Port Hedland fibre. Not a data centre. | operational | — | — | LIVEHigh confidence |
| Qenos Botany demolition and remediation Enabling works for a future industrial use. Not a data-centre project. | construction | — | — | LIVEHigh confidence |
| Qenos Altona make-safe and demolition Evidenced future use in local reporting is warehousing. | construction | — | — | REQUIRES VERIFICATIONModerate confidence |