Players

Who is building, and at what MW state

Majors are established colo and hyperscale landlords. Juniors are AI-factory and floating specialists. Announced pipeline is not built capacity. AirTrunk is a major — Australian-founded hyperscale, not a junior. Airtree Ventures is not an operator.

Majors

NEXTDC · Equinix · AirTrunk · CDC · Macquarie

Carrier-neutral colocation and wholesale

LIVE

NEXTDC

Sydney, Melbourne, Brisbane, Perth, Canberra, Adelaide, Darwin, Sunshine Coast, Port Hedland, Newman; Geelong in progress.

Built MW
288
Announced / pipeline
3030
Confidence
High confidence

FY26 results (30 June 2026): built 287.9 MW; 537 MW in progress; contracted utilisation 740 MW. 3,030 MW is operator 'total IT power' pipeline, not built capacity. M5 Melbourne is in planning for up to 1.2 GW. Announced pipeline ≠ energised MW.

International Business Exchange colocation and interconnection

REQUIRES VERIFICATION

Equinix

Sydney (SY series), Melbourne (ME), Canberra (CA1), Perth (PE).

Built MW
Not extracted
Announced / pipeline
Confidence
Moderate confidence

No independent built-MW census extracted in v0.1. Equinix publishes interconnection and IBX counts, not a DataSentinel MW ladder. Do not invent campus totals.

Hyperscale wholesale campuses for cloud and AI providers

LIVE

AirTrunk

Three Sydney campuses, two Melbourne campuses. Founder Robin Khuda.

Built MW
Not extracted
Announced / pipeline
1239
Confidence
Moderate confidence

Operator-stated campus capacities: SYD1 121 MW+, SYD2 158 MW+, SYD3 330 MW+, MEL1 276 MW+, MEL2 354 MW+ (Dec 2025). Sum ~1.24 GW is announced/planned deployable campus capacity, not a built or energised census. SYD3 is in phased construction/expansion.

Sovereign / government-weighted colocation

REQUIRES VERIFICATION

CDC Data Centres

Canberra, Sydney, Melbourne, Perth. SMAP cable-landing adjacency stated in industry coverage.

Built MW
Not extracted
Announced / pipeline
Confidence
Moderate confidence

No independent built-MW total extracted. The 1.6 GW Southgate figure is a Firmus+CDC initiative statement, not CDC built capacity.

Sovereign-leaning colocation

REQUIRES VERIFICATION

Macquarie Data Centres

Canberra (IC1/IC2/IC3), Sydney.

Built MW
Not extracted
Announced / pipeline
Confidence
Preliminary

No independent MW census in this seed. Do not copy marketing totals.

Juniors / specialists

Firmus · Mousterian

Junior is an operator class, not a judgement of ambition. Firmus has gigawatt-scale announcements. Mousterian has a 50 MW floating unit and no Australian project.