Australia firstSentinel-2 mosaic liveOpen-Meteo liveGrid adapter offAnnounced ≠ deliverable

Junior / specialist

Firmus

AI factory / neocloud. Liquid-cooled HyperCube. Builds and operates GPU campuses; also takes space on others (CDC).

REQUIRES VERIFICATIONPreliminary

Tasmania (Launceston, George Town / Long Reach, Wesley Vale proposed). Mainland via CDC (Sydney, Canberra, Melbourne, Perth stated). South Australia campuses announced (Tailem Bend, Stirling North).

HQ Australia / Singapore operating entities

Built MW
Not extracted
Contracted
900
Announced / pipeline
1600

Junior in operator class, not in ambition. Project Southgate 1.6 GW through 2028 is an initiative statement. Sep 2026: contracted capacity above 900 MW including Malaysian OpenAI capacity — not Australian energised MW. SA 2.7 GW and Tasmania 288/104/52 MW are announced/proposed. Built IT MW is not independently extracted.

Campuses

CampusLocationAnnounced MWBuilt MWStage
Launceston / St LeonardsTasmania104construction / announced
104 MW stated in Sep 2026 coverage. Southgate.
George Town / Long ReachBell Bay AMZ, Tasmania288approved / proposed
Former Gunns pulp mill pad. 220 kV on site. Direct-to-chip stated.
Wesley ValeTasmania52planning lodged
Old paper mill. 46 MW critical IT stated. Initial 26 MW on existing industrial supply claimed.
Southgate mainland + SASydney, Canberra, Melbourne, Perth, Tailem Bend, Stirling Northannounced
1.6 GW initiative and 2.7 GW SA statements. Not energised.

Why watch

  • The Australian AI-factory story: immersion/direct-to-chip, hydro-adjacent Tasmania, brownfield mill sites.
  • George Town / Long Reach is a DataSentinel-class object: former pulp-mill industrial pad, 220 kV on site.
  • Announced GW will fail or land. This product exists to keep those two states apart.

What is missing

  • Energised Australian IT MW.
  • TasNetworks connection offers.
  • CDC Southgate: whose halls, whose power.

Related pads: NSW-LIDDELL-001QLD-TOWNSVILLE-LANSDOWN-001

Evidence