SITE-AU-WA-PORT-HEDLAND-BOODARIE-001
Port Hedland / Boodarie Strategic Industrial Area
Boodarie SIA
Industrial energy system.
Site zoom
Sentinel-2 and live meteo
Cloudless mosaic on the pad, latest L2A granule, and Open-Meteo dry/wet bulb. Live weather is not a design-day and does not replace a climate study.
Sentinel-2 cloudless 2024 · Port Hedland / Boodarie Strategic Industrial Area
Approximate pad · not a cadastral survey
Deliverable MW
Announced is not deliverable
Today
High confidence1–2 MW
NEXTDC PH1 planned IT capacity 1.5 MW. That is the evidenced compute.
3 years
Preliminary1–50 MW
A step-up is conceivable only with dedicated generation. Not evidenced.
5 years
Preliminary50–250 MW
Industrial-energy colocation scenario. Competing HBI/hydrogen load is the evidenced demand.
10 years
Preliminary100–500 MW
Only with a dedicated generation and water story. Speculative.
- Pilbara is one of the world's largest industrial energy systems. That is not a published surplus for AI training.
- Existing compute is edge (PH1 1.5 MW) with cyclone and 55 °C condenser design.
- Vocus Horizon now gives a second long-haul to Perth and a path toward DJSC.
Time to power
Earliest is not likely
Earliest plausible energisation
Preliminary2031
Requires dedicated generation FID.
Likely energisation
UnverifiedNot dated
No hyperscale project.
NWIS cannot be treated like a NEM connection queue. You bring generation or you do not build.
Why here
- Industrial energy system.
- Port.
- Horizon fibre change in 2026.
- 4,000 ha SIA.
What is missing
- Spare MW.
- Water.
- A compute proponent at scale.
- Workforce housing at campus scale.
Workload fit
- Industrial / mining AIFitsThis is the product: mine-gate, port, autonomous systems. PH1 already points there.
- AI training / HPCConditionalColocation with industrial energy is the hypothesis. Surplus MW is not shown.
- Edge / regionalFitsPH1 is the existence proof at 1.5 MW.
- AI inferenceFailsWrong population geography.
- Cloud / hyperscaleFailsNot an AZ geography unless a hyperscaler decides otherwise with its own power.
- Sovereign / defenceUnknownNot the primary evidenced demand.
Energy
A 210 MW station on the map is not 210 MW for sale to a training cluster.
- Grid / NSP
- North West Interconnected System (isolated) · Horizon Power / Alinta (confirm per connection)
- Substation / voltage
- Alinta 210 MW station is on the SIA. Spare MVA not published. · Industrial. Not offered for a campus.
- Generation
- Gas, with renewable and hydrogen narratives in the Pilbara. Not contracted to compute.
- BESS / gas / RE
- Not evidenced on this object. APA pipeline traverses the estate. Pilbara RE corridors exist as a regional story. Not a campus PPA.
Required for scale
- 100 MWPreliminary
Dedicated generation, not a tap on Alinta 210 MW.
- 250 MWUnverified
A power station, water, and a fibre design beyond PH1.
Fibre
Horizon 2,000 km Perth–Port Hedland, 38 Tbps stated, with a path to DJSC. This is the 2026 change.
- Perth: 20 ms · Regional estimate via Horizon.
- Singapore: 40 ms · Geography is closer than Sydney; not a measured SLA.
- Sydney: 50 ms · Via Perth or Darwin paths.
Thermal / hazards
Hot desert / cyclone coast.
Heat is an energy penalty. The industrial energy system is the offset — if it is actually available.
Cyclone: Design-level. PH1 used tie-downs and debris protection as an existence proof at 1.5 MW.
Development
- landControl
- State SIA process. Resource processors already allocated.
- planning
- Strategic Industry. Compute would be a new use in a processing estate.
- environmental
- Industrial estate. Lot-level assessment required.
- approvalStatus
- SIA exists. Hyperscale compute not applied for.
- remediation
- Not a Qenos RAP story. Confirm per lot.
- contamination
- Industrial. Confirm.
- tenure
- SIA allocation.
- construction
- Resource-processing pipeline, not DC.
Risk
- demand
Iron processing and hydrogen are the evidenced land uses.
- power
Isolated system. Bring your own generation at scale.
Graph
- boodarie — NEAR → Port Hedland
- boodarie — CONNECTED_TO → Alinta 210 MW
- boodarie — SUPPORTED_BY → Vocus Horizon
Evidence
- VerifiedExisting
Boodarie Strategic Industrial Area comprises 4,000 ha of Strategic Industry zoned land. Alinta Energy's 210 MW gas-fired power station operates within the SIA. POSCO and Fortescue have land allocations for resource processing.
DevelopmentWA · Boodarie SIA overview · published n/a · accessed 2026-09-18
- High confidenceExisting
NEXTDC PH1 Port Hedland has a planned IT capacity of 1.5 MW. It is an edge facility for mining and port operations, not a training campus.
NEXTDC · PH1 Port Hedland Data Centre facility overview · published n/a · accessed 2026-09-18
- High confidenceExisting
Vocus Horizon is a 2,000 km fibre network between Perth and Port Hedland, stated at 38 Tbps, with a path into the Darwin–Jakarta–Singapore Cable.
w.media / Vocus · Vocus completes 2,000km Horizon fibre network linking Pilbara · published 2026-06 · accessed 2026-09-18