Mousterian Australian Opportunities

Technical compatibility, not a beauty contest

Eight initial candidates tested against an editable profile derived from Mousterian's public materials: liquid cooling, >200 kW/rack, zero municipal water, water-adjacent and floating options, factory-parallel delivery. No Australian Mousterian project is in the seed.

Profile origin

Public Mousterian Corporation materials and the Samsung Heavy Industries engineering contract (2026).

  • Fully liquid-cooled racks, halls and facilities.
  • Support for >200 kW/rack.
  • Zero evaporation or municipal water (claimed).
  • Water-adjacent and floating infrastructure; factory construction and commissioning.
  • Moored FDC units described at 50 MW IT each in the SHI contract.
  • Project Zeus (Houston, ~500 MW hybrid) and Project Sandpiper (San Jose, ~860 MW) listed as plans, not energised Australian sites.
  • No Australian Mousterian project is in this seed.
  • 50 MW/unit is a published design target, not a connected Australian MW.
  • Zero municipal water is a design claim to test sites against, not a verified operating result in Australia.

Editable profile

Derived from Mousterian public claims. Change the numbers. Ranking is compatibility, not a score.

SITE-AU-QLD-TOWNSVILLE-LANSDOWN-001

Townsville / Lansdown Eco-Industrial Precinct

Conditional

4 fit · 2 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)FitsSeeded 5-year scenario is 50–250 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWConditionalGreenfield industrial lots can be designed for >200 kW/rack. Nothing is designed.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, immersion.
  • Zero municipal waterConditionalRaw water pipeline from Ross Dam is in design — proposed, not operating. Not municipal potable by description.
  • Floating / water-adjacent preferredFitsThe precinct is inland at Woodstock/Calcium, ~40 km south of Townsville and not on the harbour. Floating architecture would be a Port of Townsville proposition, not Lansdown itself. Port-adjacent floating is a separate object.
  • Fibre routes ≥ 2UnknownNot verified to the precinct. Single-corridor risk to Brisbane is the default assumption until two routes are shown.
  • Site area ≥ 20 haFits2,200 ha precinct. Individual compute-suitable lots are not allocated. Lot configuration changes with tender outcomes.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. A transmission line near Woodstock is not a 250 MW connection offer. CopperString in 2032 is not spare capacity sitting in Townsville in 2028.

SITE-AU-NT-DARWIN-WEDDELL-001

Darwin / Weddell industrial area

Conditional

3 fit · 4 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 0–500 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWConditionalCan be designed for >200 kW/rack. Not designed.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, immersion.
  • Zero municipal waterConditionalNot verified for GW-scale evaporative plant. Do not assume it.
  • Floating / water-adjacent preferredFitsWeddell is inland of Darwin Harbour. Harbour floating would be a different site. Darwin Harbour cyclone and biosecurity regimes would dominate.
  • Fibre routes ≥ 2ConditionalA second international path (Bosun / Inligo) is planned, not a substitute for diverse laterals to Weddell.
  • Site area ≥ 20 haFits185 ha exclusivity at Weddell, ~30 km south of Darwin CBD, adjacent to a proposed Darwin Energy Hub. Exclusivity ≠ development consent.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. DJSC exists. 2 GW of gas plant does not.

SITE-AU-WA-PORT-HEDLAND-BOODARIE-001

Port Hedland / Boodarie Strategic Industrial Area

Conditional

3 fit · 3 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 50–250 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWConditionalIndustrial SIA pads can be designed for high density. Heat is the constraint, not floor plate.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, seawater-heat-rejection.
  • Zero municipal waterConditionalPilbara water is contested industrial water. Do not assume municipal or evaporative supply.
  • Floating / water-adjacent preferredFitsPort Hedland harbour is nearby via corridors, not the SIA core. Harbour is a working bulk-export port. Floating compute would fight shipping, cyclone mooring and biosecurity.
  • Fibre routes ≥ 2UnknownHorizon is described as a second route. Site diversity to a Boodarie lot is not surveyed.
  • Site area ≥ 20 haFits4,000 ha Strategic Industry. POSCO and Fortescue have allocations for iron processing. Do not treat the SIA as vacant.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. A 210 MW station on the map is not 210 MW for sale to a training cluster.
Conditional

3 fit · 2 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 100–500 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWConditionalGreenfield pad on a power station site can be designed for >200 kW/rack. Not designed.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, immersion.
  • Zero municipal waterUnknownLake Liddell remains a key water asset for Bayswater. Surplus for a campus is not verified.
  • Floating / water-adjacent preferredFitsLake Liddell is a cooling-water asset for Bayswater. Floating compute on the lake is a hypothesis, not a proposal, and would compete with remaining generation water use until 2033.
  • Fibre routes ≥ 2UnknownNot verified to the pad.
  • Site area ≥ 20 haFitsAGL publishes a 10,000 ha combined Bayswater and Liddell landholding. That is not the developable pad for a campus.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. Transmission connections are being retained. That is not a published MW figure a developer can take to a bank.

SITE-AU-VIC-ALTONA-QENOS-001

Altona petrochemical precinct

Conditional

2 fit · 2 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 50–150 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWUnknownUnverified. Liquid cooling is architecturally possible on a remediated industrial pad; not designed.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, seawater-heat-rejection, air.
  • Zero municipal waterConditionalMunicipal water should not be assumed for a high-density campus.
  • Floating / water-adjacent preferredFitsPort Phillip is nearby. The Qenos land itself is a terrestrial industrial parcel. Floating architecture would be a separate marine consent, not implied by the landholding.
  • Fibre routes ≥ 2UnknownMetro-typical; site diversity unverified.
  • Site area ≥ 20 haUnknownHistoric petrochemical landholding on Kororoit Creek Road. Exact hectare figure for the Qenos parcel is not independently verified here.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. Industrial electrical infrastructure existed. Commercially connectable spare MW is not verified.

SITE-AU-NSW-BOTANY-QENOS-001

Botany Industrial Park — former Qenos

Conditional

2 fit · 2 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 50–200 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWUnknownUnverified pending RAP and structural design.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, seawater-heat-rejection, floating.
  • Zero municipal waterConditionalDo not assume municipal water for cooling.
  • Floating / water-adjacent preferredFitsBotany Bay / Port Botany is adjacent. Floating would be a port/marine consent under a separate regime, with airport OLS as an additional constraint.
  • Fibre routes ≥ 2UnknownMetro-typical; site diversity unverified.
  • Site area ≥ 20 haUnknownQenos parcel within Botany Industrial Park. Broader park has multiple owners (Orica, Indorama, Ixom). Do not treat the whole park as one title.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. Infrastructure existed for petrochemical load. Connectable spare MW is not verified.

SITE-AU-NSW-NEWCASTLE-HUNTER-001

Newcastle / Hunter River industrial waterfront

Conditional

2 fit · 2 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 100–400 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWUnknownUnverified. Waterfront liquid cooling is the architectural hypothesis.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop, floating, seawater-heat-rejection.
  • Zero municipal waterUnknownRiver/port adjacent. Extraction licences are not evidenced.
  • Floating / water-adjacent preferredFitsHunter River and port waters are the reason this site is in the Mousterian set. Marine consent, shipping channels and flood are first-order.
  • Fibre routes ≥ 2ConditionalCorridor diversity ≠ site diversity.
  • Site area ≥ 20 haUnknownThis object is a precinct, not a single lot. Mayfield, former steelworks and port lands should be disaggregated before any commercial work.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. Infrastructure exists in the Hunter. A waterfront campus connection is not evidenced.

SITE-AU-WA-KARRATHA-MAITLAND-001

Karratha / Maitland Strategic Industrial Area

Conditional

2 fit · 1 conditional · 0 fail — not a composite score

  • Minimum campus 50 MW (2030s scenario, not an offer)ConditionalSeeded 5-year scenario is 50–200 MW (preliminary). Scale is conceivable on paper. This is not a grid offer.
  • Rack density ≥ 200 kWUnknownUnverified.
  • Liquid coolingFitsOptions include direct-to-chip, closed-loop.
  • Zero municipal waterUnknownContested. Not verified.
  • Floating / water-adjacent preferredFitsDampier / port waters are a working LNG and bulk geography. Floating is a harsh marine and cyclone problem, not a default.
  • Fibre routes ≥ 2UnknownUnverified.
  • Site area ≥ 20 haUnknownMaitland SIA is a designated strategic industrial area. Hectares available for a compute lot are not verified in this build.
  • N+1 powerUnknownRedundancy is a design choice, not an evidenced site attribute in v0.1. Energy-rich region. Connectable surplus not shown.